100th Street Interchange at I-35/80

Description


Proposed is the construction of an interchange at 100th Street and Interstate 35/80.  In 2018 the ramps are to be paved.

Project Status Update - 10/10/18

The contractor is working on paving the new lanes on to the Interstate and connecting the new 100th Street ramps to the Interstate. Construction at the 100th Street Interchange will be completed by the afternoon of October 15th to allow for the western half of the interchange to open (westbound on ramp and eastbound off ramp). After the west half of the 100th Street Interchange is open to traffic, the contractor will work towards opening the east half. The west half of the 86th Street Interchange closure will be delayed until the spring of 2019 for reconstructing the ramp connections to the interstate. Plum Drive and Northpark Drive will be used as detours during the 86th Street Ramp closures.

The outside lanes of 100th Street are closed during this construction.