Project Description:

This project provides for the reconstruction of Meredith Drive from 156th Street west to ¼ mile east of 170th Street as a four-lane roadway with left-turn lanes including grading, and storm sewer. The paving will be portland cement concrete with two 26-foot wide paving sections and a 28-foot grass median and a 10-foot trail on the north side. This is a joint project with the City of Clive. It is anticipated that this project would be completed by the end of November 2019.

Project Status Update - 11/04/19

Stage 1 is complete and open to traffic. Temporary single lanes closures will be required for backfill and sidewalk/trail construction. Phase 2 is closed for construction from the west side of 162nd Street to 170th Street.

As the weather allows, the contractor will be grading for the construction of the sidewalks and trails in Phase 1. The driveways in Phase 1 are scheduled for this week.

The contractor is working on grading in preparation for paving. The contractor anticipates paving the mainline paving in Phase 2 the week of November 11th.

An official detour route is established on 156th Street, Douglas Parkway and 170th Street. The Police and Fire Departments have been notified of the closed areas.